A vacant warehouse located on Wren Road was in desperate need of a roof replacement.
Upon first inspection, it was extremely obvious to our ACR Roofing estimators that the original metal roof was in terrible condition, and as you can see in the pictures. In addition to the corrosion eating away at the metal roof material, there lacks any form of safety mesh. Therefore, deeming the factory non-compliant and an extreme OH&S concern.
In conclusion, the only option would be for us to remove and replace the metal roof. As well as install new safety mesh and sarking foil.
When replacing the roof, we complete the works in stages. Each day, an area is removed then safety mesh and sarking foil is installed. Then, the new roofing materials are installed above. In this case, we installed new BlueScope Plain Zincalume Corrugated roof material. This process ensures that the building remains watertight whilst our team complete the works.
Wren Road Roof Replacement
Due to the height of the roof we craned all materials onto the roof. We also installed safety rail around the full perimeter of the building. Like any other roof replacement project, safety is always our number 1 priority!
In under 2 weeks, our team removed the old roof sheets, gutters and downpipes. In addition to installing Zincalume Corrugated roofing material, we installed Ampelite Industrial Translucent sheeting. The translucent sheets were installed in one full length, in the centre of each bay. We also allowed to install new Zincalume gutters, flashings and downpipes.
Like all commercial roof replacements completed by ACR Roofing, this was a success. Our team pride ourselves on completing roof replacement projects and believe we are the best in the business.
The before and after photos speak for themselves! Another fantastic job completed by our fantastic team.