Asbestos Cement Roofing Replacement – Burwood East

ACR Roofing professionals inspected the asbestos cement roof on a single story home, located in the leafy south-east suburb of Burwood East.
In most cases, the only option for an asbestos roof is for a complete removal and replacement of a new roof; and so our client found themselves in need of an Asbestos roof replacement & replacement.

Asbestos Removal in Melbourne is a highly regulated industry and only licenced practitioners can complete the removal and replacement of asbestos roofing. ACR Roofing treats Melbourne asbestos removal very seriously and comply with WorkSafe & EPA standards. Notifying WorkSafe and neighbouring residence before the removal takes place

ACR installed safety rail and completed the entire Asbestos Roof Replacement in just two days. Our team removed the old Asbestos Cement Roofing, installed 60mm foil-faced roof insulation blanket and brand new Colorbond roof materials. The client chose the colour ‘Woodland Grey’ for all Colorbond materials installed.

Our team completed yet another successful roof replacement; leaving both ACR Roofing and the client satisfied with the end result.
With over 46 years’ experience completing Asbestos Removal in Melbourne, it’s no wonder ACR Roofing are considered the number one roof replacement company in Melbourne.

The thought of an asbestos roof replacement may seem confusing..
ACR Roofing simplify the process into
Seven steps for an uninterrupted Roof Replacement

1 Engage ACR Roofing-

Licensed asbestos removalist and roof plumbers; site meetings/ briefings, for you and your staff. Learn how the removal- replacement takes place.

2 Notification-

Our Team will notify WorkSafe and the neighbouring businesses/ properties of the works we are completing.

3 Preparation-

Install all safety equipment, hand rail, scaffold, access tower, crane and load all materials onto the roof area/ site.

4 Removal-

Remove a section of asbestos each day, decontaminate all, engage an independent hygienist to issue a clearance certificate.

5 Replacement-

Installation of all new materials, safety mesh, roof insulation blanket, gutters, roof sheeting, translucent sheeting.

6 Completion-

Final asbestos clearance certificate issued and received, new roof installed and completely caped- watertight.

7 Hand Over-

ACR Director completes a final inspection. Client receives EPA waste dockets, BlueScope Warranty, VBA Plumbing compliance certificate.